少妇人妻一级A毛片无码,国产精品一区二区三区在线观看,国产寡妇婬乱A毛片视频中文,国产日韩精品无码去免费专区国产,欧美精品在线免费观看,毛片免费在线播放,毛片免费在线视频,免费毛片大全,一级一级一级毛片免费毛片,国产农村妇女精品一二区 ,国产成人精品免费视频网页大全,国产精品成年片在线观看,亚洲欧美另类久久久精品能播放的,国产精品青草久久久久福利99 ,日产精品久久久久久久性色,91久久91久久精品麻豆,sss亚洲国产欧美一区二区,美女张开腿喷水高潮在线观看,色欲合久久久无码中文字幕波多

Hello, welcome to visit Shandong Linyi Kuntai Machinery Equipment Co., Ltd official website!
13583992199 13562968979
Shandong Linyi Kuntai Machinery Equipment Co., Ltd
HOT KEY WORDS:used ball mill,used crusher,NE elevator,old ball mill
Loading......
Your location: Home > The ball mill installation test run
News

The ball mill installation test run

Date: 2014/7/29 18:16:55 Read: 3583 times

Commissioning: 
Ball mill installation is complete, after inspection, the empty test run can be achieved. The ball mill of ball mill in the test run by skilled operators, ball mill and strictly abide by the safety operation procedures. 
(a) continuous operation of idle running time not less than 12-24 hours a day, found that the problem should be resolved in a timely manner during operation. 
(2) the idle running of commissioning can be normal load test run. The load test run in every phases. Load operation shall be carried out according to the condition of discharge in the feed, avoid unnecessary grinding ball and the cylinder liner and damage. 
1, add appropriate material, and a third the number of steel ball (see the largest amount with ball mill assembly drawing) test run 12 to 24 hours. 
2, join to two-thirds of the number of steel ball works 24 to 48 hours. 
3, according to the ball mill discharge conditions, production of qualified products, with reference to the same kind of ball-mill machine actual loading quantity, determine the ball loading quantity of the ball mill machine, step to less than 72 hours of test run. 
(3) the increase of the load and test run of the length of time, with the size of the gear and gear reducer of the running-in condition (temperature, noise, tooth contact, etc.) as a basis for sure. In front of the tooth surface contact precision did not meet the design requirements, shall not operate at full capacity. (4) commissioning of cooling and lubrication system should be working properly. Main bearing, bearing, reducer temperature should be normal. 
(5) into the two-thirds of the number of steel ball test run 24-48 hours later, should check and tighten all bolts again. 
(6) the commissioning work should earnestly each record. 
CATEGORY
PRODUCTS
屯门区| 元氏县| 黔江区| 西城区| 康平县| 调兵山市| 天气| 莱西市| 宁波市| 进贤县| 龙井市| 万源市| 安福县| 洪雅县| 旺苍县| 郑州市| 成武县| 益阳市| 改则县| 宝清县| 浮梁县| 成都市| 剑阁县| 左贡县| 栾城县| 芜湖县| 尼玛县| 黄陵县| 渭南市| 乃东县| 鄄城县| 成安县| 金堂县| 葫芦岛市| 雷山县| 温州市| 洛扎县| 德清县| 洪雅县| 铜山县| 桐梓县|